Deluca Project #6

A lot has happened since our last update! We are in the final stages of this great project. The exterior finishing touches are going on  along with all the curbs, sidewalks, & parking lot being prepped and poured.

The main warehouse is now complete and all the coolers and equipment are starting to be installed and placed. We used a combination of metal and TrussCore. The coffee manufacturing room is studded out completely with metal studs and covered fully with TrussCore to make it Food Grade Compatible.

All of the Allweather Apex Alloy Heat smart 6 windows have been installed  along with all the aluminum entrance door. By going with the heat smart 6 it will eliminate almost all of the uv rays keeping the cooling system down and make it more energy efficient.

The office pan deck floor has been installed and the concrete has been poured over top for the office area. The stud walls are being erected and the offices & staff room are starting to take shape.

 

 

Deluca Project #5

The crews have been very busy since the last update. The last of the 50’3″ ICF fire wall had been poured and the steel beams and columns placed and ready for roof trusses.

We started off with installing Flat Top trusses that are 8’6″ high x 70′ long.The crews pre-built the sections on the ground and we craned them into place. Once the flat tops were installed the Mono truss were placed on top of the flat top. The 13′ high at the peak Mono Truss will give the slope of the roof towards the back. The front retail area is also getting all the Flat Top trusses installed.

While two of the crews where working on the trusses one crew was starting to wrap the Tyvek House wrap for weather proofing. We added and extra layer of 4×8-1″ plastispan insulation to the exterior before wrapping with the house wrap for added R value. The total R value for the walls on this building will be a R27 as per building code.

 